This projected involved a series of phased new build and refurbishment works over a number of years and ranging in value from £75,000 to £1.2 million.
Phase 1: 1500m2 extension to hatchery carried out in an existing busy working environment.
Phase 2: A reinforced earth retaining structure to allow factory extension, drainage connections, installation of a rainwater recycling system and associated site works.
Phase 3: Portal frame factory extension to working hatchery.
Phase 4: Demolition works of old warehouse, drainage and associated site works. Refurbishment of office accommodation and construction of new offices with staff changing and welfare accommodation