Holywood Sewers Network

Client:
Northern Ireland Water, Engineering Procurement, Holywood Sewer Network Improvements
Contract Duration:
78 Weeks
Project Description:
Installing Underground Pipes & Pumping Equipment
Design Team:
Architect : McAdam Design
CLICK IMAGES TO VIEW LARGER

This award-winning project comprised of an up-grade to the existing works, installation of new underground pipe networks, associated pumping equipment and M&E. The majority of the works involved deep tunneling below public areas and transport networks.

The new pumping station enables the closure of three combined sewer overflows known as Strathearn Court, Palace Barracks and Jacksons Road.  The new pumping station has also intercepted existing foul sewage flows from the adjacent MOD facility and the nearby Belfast Harbour Estate and pump them to the Kinnegar WwTW for treatment.